How Long Does Pool Construction Take?
Timeline varies by system type, weather, and complexity. Here's what to expect.
Desjoyaux Timeline
- Week 1-2: Design, permits, lot prep
- Week 3-4: Foundation and wall installation
- Week 5-7: Plumbing, electrical, interior finish
- Week 8: Final testing, opening
Gunite Timeline
- Week 1-2: Excavation and prep
- Week 3-6: Gunite spraying and curing
- Week 7-10: Plumbing, electrical, finish
- Week 11-12: Curing and opening